Translate

Material Requirements Planning



 
1.0 INTRODUCTION  Material requirements planning (MRP) is a computer-based information system  for ordering and scheduling of dependent-demand inventories (e.g. raw  materials, component parts, and subassemblies). (Recall that dependent demand  is the demand for items that
are subassemblies or component parts to  be used in the production of finished goods). 

What is involved in MRP is the translation of a production plan for a specified  number of finished products into requirements for component parts and raw  materials working backward, using lead time information to determine when  and how much to order. 

MRP is as much a philosophy as it is a technique, and as much an approach to  scheduling as it is to inventory control. MRP begins with a schedule of finished  goods that is converted into a schedule of requirements for subassemblies,    components parts, and raw materials needed to produce the finished items in  the specified time frame. What this amounts to, is that MRP is designed to  answer three questions: What is needed? How much is needed? And when it is  needed? The primary inputs of MRP necessary to answer these questions are
(i)  a bill of material, which tells the composition of a finished product; (ii) a  master schedule which tells how much finished product is desired and when;  and (iii) an inventory records file, which tells how much inventory is on hand  or on order. This information is then processed to determine the planning  horizon. 

Outputs from the process include planned-order schedule, order releases,  changes performance-control reports, planning repots and exception reports.  These inputs and output are discussed in more detail in subsequent sections. 

2.0 OBJECTIVES 
After completing this note, you should be able to: 
(i) Describe the conditions under which MRP is most appropriate. 
(ii) Describe the input, outputs and nature of MRP processing. 
(iii) Explain how requirements in a master production schedule are translated  into material requirements for lower-level items. 
(iv) Discuss the benefits and requirements of MRP. 
(v) Explain how an MRP system is useful in capacity requirements  planning. 
(vi) Outline the potential benefits and some of the difficulties users have  encountered with MRP. 
(vii) Describe MRP II and how it relates to MRP. 

3.0 MAIN CONTENT 
3.1 MRP Inputs  As already mentioned in proceeding section, an MRP system has three major  sources of information: a master schedule, a bill- of-material file, and an  inventory records file. Let's consider each of these inputs. 
3.1.1 The Master Schedule  The master schedule states which end items are to be produced, when they are  needed, and in what quantities. Figure 12.1 illustrates a portion of a master  schedule that shows planned output for end items X for the planning horizon.  The schedule indicates that 100 notes of X will be needed (e.g., for shipments  to customers) at the start of week 4 and that another 150 notes will be needed at  the start of week 8.   

Figure 12.1. A portion of master schedule. 

Week Number 
Item X 1 2 3 4 5 6 7 8
 Quantity         100 150 

The quantities in a master schedule come from a number of different sources,  including customer orders, forecasts, orders from warehouses to build up  seasonal inventories, and external demand.  The master schedule separates the planning horizon into a series of time  periods or time buckets, which are often expressed in weeks.

However, the  time bucket need not be of equal length.  It is important that the master schedule cover the stacked or cumulative lead  time necessary to produce the end items. This cumulative lead time is the sum  of the lead times that sequential phases of a process require, from ordering of  parts or raw materials to completion of final assembly.  Stability in short-term production plans is very important; without it, changes  in order quantity and/or timing can render material requirements plans almost  useless. To minimize such problems, many firms establish a series of time  intervals, called time fences, during which changes can be made to orders.

For  example, a firm might specify time fences of 4,8, and 12 weeks, with the  nearest fence being the most restrictive and farthest fence being less restrictive.  Beyond 12 weeks changes are expected; from 8 to 12 weeks, substitutions of  one end item for another may be permitted as long as the components are  available and the production plan is not compromised; from 4 to 8 weeks, the  plan is fixed, but small charges may be allowed; and the plan is frozen out to  the four-week fence. 

3.1.2 The Bill-of-Material File.  A bill of materials (BOM) containing a listing of all the assemblies, subassemblies,  parts, and raw materials that are needed to produce one note of a  finished product. This means that each finished product has its own bill of  materials.  The listing in BOM is hierarchical; it shows the quantity of each item needed to  complete one note of the following level of assembly. The nature of this aspect  of a BOM is perhaps grasped most readily by considering a product structure  tree, which provides a visual depiction of the subassemblies and components  that are needed to assemble a product. Figure 12.2 shows a product tree for a  chair.  

 Figure 12.2: Product Structure Tree  Chair  
A product structure tree is useful in illustrating how the bill of materials is used  to determine the quantities of each of the ingredients (requirements) needed to  obtain a desired number of end items

 3.1.3 The Inventory Records File  The inventory records file is used to store information on the status of each  item by time period. This includes gross amount on hand. It also includes other  details for each item, such as supplier, lead time, and lot size - changes due to  stock receipts and withdrawal, canceled orders, and similar events also are  recorded in this file. 

3.2 MRP Processing  MRP processing takes the end-item requirements specified by the master  schedule and "explodes" them into time-phased requirements for assemblies,  parts, and raw materials using the bull of materials offset by lead times.  The quantities that are generated by exploding the bill of materials are gross  requirements. It is the total expected demand for an item or raw material during  each time period without regard to the amount on hand. For end items, these  quantities are shown in the master schedule; for components, these quantities  equal the planned-order releases of their immediate "parents" 

Scheduled Receipt: - Open orders scheduled to arrive from vendors or  elsewhere in the pipeline by the beginning of a period. 
Projected on hand: - The expected amount of inventory that will be on hand at  the beginning of each time period; schedule receipts plus available inventory  from last period. Net-requirements: - The actual amount needed in each time  period. 
Planned-order receipts: - The quantity expected to be received by the  beginning of the period in which it is shown. Under lot-for-lot ordering, this  quantity will equal net requirements. Under lot-size ordering this quantity may  exceed net requirements. Any excess is added to available inventory in the next  time period.  Planned-order releases: - Indicates a planned amount to order in each time  period; equal planned-order receipts offset by lead time. This amount generates  gross requirements at the next level in the assembly or production chain. When  an order is executed, it is removed from "planned-order releases" and entered  under "Scheduled receipts" 

Let us illustrate MRP processing with the following example. 

Suppose firm that produces wood shutters and bookcases has received two  orders for shutters: one for 100 shutters and one for 150 shutters. The 100-note  order is due for delivery at the start of week 4 of the current schedule, and the  150-note order is due for delivery at the start of week 8. Each shutter consists of    four slatted wood sections and two frames. The wood sections are made by the  firm, and fabrication takes one week. The frames are ordered and lead time is  two weeks. Assembly of the shutters requires one week. There is a scheduled  receipt of 70 wood sections in (i .e. at the beginning of) week 1. Determine the  size and timing of planned-order releases necessary to meet delivery  requirements under each of these conditions:  Lot-for-lot ordering (i e order size equal to net requirements)

 Lot-size ordering with a lot size of 20 notes for frames and 70 notes for wood  sections to answer tree question, you first develop a master schedule as  follows: 

Week number 1 2 3 4 5 6 7 8 
Quantity 100 150
 

Next, using the master schedule, determine gross requirements for shutters.  Then, compute net requirements. Assuming lot-for-lot ordering, determine  planned-order receipt quantities and the planned - order release timing to  satisfy the master schedule 

Since the master schedule calls for 100 shutters to be ready for delivery, and no  shutters are projected to be on hand at the start of week 4, the next  requirements are also 100 shutters. Therefore planned receipts for week 4  equals 100 shutters. Some shutters are assembled during week 7 in order to be  available for delivery at the start of week 8. 

The planned-order release of 100 shutters at the start of week 3 means that 200  frames (gross requirements) must be available at that time. Since more are  expected to be on hand, this generates net requirements of 200 frames and  necessitates planned receipts of 200 frames by the start of week 3. With a two week  lead time, this means that 200 frames must be ordered at the start of week  1.

Similarly, the planned-order release of 150 shutters at week 7 generates  gross net requirement 300 frames for week 7 as well as planned receipts for    that time. The two-week lead time means frames must be ordered at  the start of week 5.  The planned-order release of 100 shutters at the start of week 3 also generates  gross requirements of 400 wood sections at that time.

However, because 70  wood sections are expected to be on hand, net requirements are 400-70 =330.  This means a planned receipt of 330 by the start of week 3. Since fabrication  time is one week, the fabrication must start (planned order release) at the  beginning of week 2.  Similarly, the planned-order release of 150 shutters in week 7 generates gross  requirements of 600 wood sections at that point. Since no on-hand inventory of  wood sections is projected, net requirements are also 600, and planned-order  receipt is 600 notes. Again, the one week lead time means 600 sections are  scheduled for fabrication at the start of week 6. 

Finally under lot-size ordering, the only difference is the possibility that  planned receipts will exceed net requirements. The excess is recorded as  projected inventory in the following period. For example, the order size for  frames is 320 notes. Net requirements for week 3 are 200; thus, there is an  excess of 320-200 = 120 notes, which become projected inventory in the next  week. Similarly, net frame requirements of 180 notes are 140 less than the 320  order size; again, the excess become projected inventory in week 9.

The same  thing happens with wood sections; an excess of planned receipt in weeks 3 and  7 is added to projected inventory in weeks 4 and 8. Note that the order size  must be in multiples of the lot size; for week 3 it is 5 times 70 and for week 7 it  is 9 times 70.  The importance of computer becomes evident when you consider that a typical  firm would have not one but many end items for which it needs to develop  material requirements plans, each with its own set of components.

 Inventories on hand and on order, schedules, order releases, and so on must all  be up dated as changes and rescheduling occurs. Without the aid of a computer,  the task would be almost hopeless; with the computer, all of these things can be  accomplished with much less difficulty. 

Updating the System. The two basic systems to update MRP records are  regenerative and net change. A regenerative system is updated periodically; a  net-change system is continuously updated.  A regenerative system is essentially a batch-type system, which compiles all  changes (e.g. new orders, receipts) that occur within the time interval (e.g.  week) and periodically updates the system. Using that information, a revised  production plan is developed (if needed) in the same way that the original plan  was developed (e.g. exploding the bill of materials level by level).   

In a net-change system, the basic production plan is modified to reflect changes  as they occur. If some defective purchased parts had to be returned to a vendor,  this information is entered into the system as soon as it becomes known. Only  the changes are exposed through the system, level by level; the basic plan  would not be regenerated.  The regenerative system is best suited to fairly stable systems, whereas the netchange  system is best suited to systems that have frequent changes. The  obvious disadvantage of a regenerative system is the potential amount of lag  between the time information becomes available and the time it can be  incorporated into the material requirements plan.

On the other hand, processing  costs are typically less using regenerative systems; changes that occur in a  given time period could ultimately cancel each other, thereby avoiding the need  to modify and then remodify the plan. The disadvantages of the net-change  system relate to the computer processing costs involved in continuously  updating the system and the constant state of flux in a system caused by many  small changes. On way around this is to enter minor changes periodically and  major changes immediately. The primary advantage of the net-change system  is that management can have up-to-date information for planning and control  purposes. 

3.3 MRP Outputs 
MRP systems have the ability to provide management with a fairly broad range  of outputs. These are often classified as primary reports, which are the main  reports, and secondary reports, which are optional outputs. 

3.3.1 Primary Reports 
Production and inventory planning and control are part of primary reports.  These reports normally include the following:  (1) Planned orders, a schedule indicating the amount and timing of future  orders.  (2) Order releases, authorizing the execution of planned orders.  (3) Changes to planned orders, including revisions of due dates or order  quantities and cancellations of orders. 

3.3.2 Secondary Reports 
Performance control, planning, and exceptions belong to secondary reports.  (1) Performance-control repots are used to evaluate system operation. They  aid managers by measuring deviations from plans, including missed    deliveries and stock-outs, and by providing information that can be used  to assess cost performance.  (2) Planning reports are useful in forecasting future inventory requirements.  They include purchase commitments and other data that can be used to  assess future material requirements.  (3) Exception reports call attention to major discrepancies such as late and  overdue orders, excessive scrap rates, reporting errors and requirements  for none existent parts.  The wide range of output generally permits users to adapt MRP to their  particular needs. 

3.3.3 Safety Stock 
Theoretically, inventory systems with dependent demand should not require  safety stock below the end-item level. This is one of the main advantages of an  MRP approach. Supposedly, safety stock is not needed because usage  quantities can be projected once the master schedule has been established.  Practically, however, there may be exceptions. For example, a bottleneck  process or one with varying scrap rates can cause shortage in downstream  operations. However, a major advantage of MRP is lost by holding safety stock  for all lower-level items.

When lead times are variable, the concept of safety  time instead of safety stock is often used. This results in scheduling orders for  arrival or completion sufficiently ahead of the time they are needed in order to  eliminate or substantially reduce the element of chance in waiting for those  items. Frequently, managers elect to carry safety stock for end items, which are  subject to random demand and for selected lower-level operations when safety  time is not feasible.

 3.3.4 Lot Sizing 
Choosing a lot size to order or for production is an important issue in inventory  management for both independent- and dependent-demand items. This is called  lot sizing. For independent-demand items, economic order sizes and economic  run sizes are often used.  Mangers can realize economies of scale by grouping order or run sizes. This  would be the case if the additional cost in covered by holding extra notes until  they were used led to a saving in set up or ordering cost. This determination  can be very complex at times. Let's consider some of the methods used to  handle lot sizing. 

3.3.4.1 Lot-for-lot ordering 
The order or run size for each period is set equal to demand for that period.  This method was demonstrated in the example in section 3.3. Not only is the    order size obvious, but it also virtually eliminates holding casts for parts carried  over to other periods. Hence, lot-for-lot ordering minimizes investment in  inventory. Its two chief draw backs are that it usually involves many different  order sizes and thus cannot take advantage of the economies of fixed order size  and it involves a new setup for each run.

 3.3.4.2 Economic Order Quantity Model 
Sometimes economic order quantity models (EOQ) are used. They can lead to  minimum costs if usage is fairly uniform. This is sometimes the case for lowerlevel  items that are common to different parents and for raw materials.  However, the more lumpy demand is, the less appropriate such an approach is. 

3.3.4.3 Fixed - Period Ordering 
This type of ordering provided coverage for some predetermined number of  periods (e.g., two or three). A simple rule is; order to cover a two period  interval. The rule can be modified when common sense suggests a better way.  For example, take a look at the demand shown in Figure 12.5. Using a twoperiod  rule, an order size of 120 notes would cover the first two period. The  next two periods would be covered by an order size of 81 notes. However, the  demand, in period 3 & 5 are so small, it would make sense to combine them  both with the 80 notes and order 85 units. 

 
Figure 12.5: Demand of part 

 3.3.4.4 Part-Period Model  The term part-period refers to holding a part or parts over a number of periods.  For example, if 10 parts were held for two periods, this would be 10x2 = 20  part periods. The economic part period (EPP) can be computed as: 

EPP = Setup Cost 
Note holding cost per period. 

In order to determine an order size that is consistent with EPP, various order  sizes are examined for a planning horizon, and each one's number of part  periods is determined. The one that comes closest to the EPP is selected as the    best lot size. The order sizes that are examined are based on cumulative  demand. The following example illustrates this approach.  Now use the part-period method to determine order sizes for this demand  schedule: set cost is N80 per run for this item, and note-holding cost is N95 per  period. 

Solution  

3.4 Capacity Requirements Planning  One of the most important features of MRP is its ability to aid manager in  capacity planning. As noted, a master production schedule that appears feasible  on the surface may turn out to be far less feasible in terms of the resources  requirements needed for fabrication and /or subassembly operations of lowerlevel  items. 

Capacity requirement planning is the process of determining shortage capacity  requirements. The necessary inputs include planned-order releases for MRP,  the current shop load, routing information and job times. Outputs include load  report for each work center. When variances (under loads or over loads) are  projected, managers might consider remedies such as alternative routing,  changing or eliminating lot splitting. Moving production forward or back ward  can be extremely challenging because of precedence requirements and  availability of components. 

The capacity planning begins with a proposed or tentative master production  schedule that must be tested for feasibility and possibly, adjusted before it  becomes permanent. The proposed schedule is processed using MRP to  ascertain the material requirements the schedule would generate. These are then  translated into resource ( i e capacity) requirements often in the form of a series  of load reports for each department or work p center, which compares known  and expected future capacity requirement with projected capacity availability. 

An important aspect of capacity requirements planning is the conversion of  quantity requirements into labour and machine requirements. This is  accomplished by multiplying each period's quantity requirements by standard  labor and/or machine requirements per note. For instance, if 100 notes of  product A are scheduled in the fabrication department, and each note has a  labor standard time of 2 hours and a machine standard time of 1.5 hours, then  100 notes of A convert into these capacity requirements. 

Labor:- 100 notes x 2 hours/note = 200 labor hours 
Machine: 100 notes x 1.5 hours/note = 150 machine hours 

These capacity requirements can then be compared with available department  capacity to determine the extent to which this product utilizes capacity. For  example, if the department has 200 labour hour, and 200 machine hours  available, labor utilization will be 100 percent because of all of the labor  capacity will be required by this product. However, machine capacity will be  underutilized. 

Required X 100 =       150hours X 100 = 75 percent. 
Available                     200 hours   

Underutilization may mean that unused capacity can be used for other jobs;  over utilization indicates that available capacity is insufficient to handle  requirements. To compensate, production may have to be rescheduled or  overtime may be needed. 

3.5 Benefits and Requirements of MRP 
3.5.1 Benefits  MRP offers a number of benefits for the typical manufacturing or assembly  type of operation, including: 
(1) Low levels of in-process inventories 
(2) The ability to keep track of material requirements. 
(3) The ability to evaluate capacity requirements generated by a given  master schedule. 
(4) A means of allocating production time.  A range of people in a typical manufacturing company are important users of  information provided by an MRP system. Production mangers who must  balance work loads across departments and make decisions about scheduling  work, and plant foremen, who are responsible for issuing work orders and  maintaining production schedules, also rely heavily on MRP output. Other  users include customer service representatives, who must be able to supply  customers with projected delivery dates, purchasing managers, and inventory  managers. The benefits of MRP depend on large measure on the use of a  computer to maintain up-to-date information on material requirements.

 3.5.2 Requirements  In order to implement and operate an effective MRP system, it is necessary to  have: 
(1) A computer and the necessary software programs to handle  computations and maintain records. 
(2) Accurate and up-to-date 
(a) Master schedule 
(b) Bills of materials 
(c) Inventory records 
(3) Integrity of file data  On the whole, the introduction of MRP has led to a major improvement in  scheduling and inventory management but it has not proved to be the cure-all    that many hoped it would be. Consequently, manufacturers are beginning to  take a much broader approach to resource planning one such approach is  referred to as MRP 11. 

3.6 MRP II  MRP II refers to manufacturing resources planning. It represents an effort to  expand the scope of production resource planning and to involve other  functional areas of the firm in the planning process. A major purpose of MRP  His to integrate primary functions and other functions such as personnel,  engineering and purchasing in the planning process. 

Material requirement planning is at the heart of the process. Process begins  with an aggregation of demand from all sources (e.g. firm orders, forecasts,  safety stock requirement). Production, marketing and finance personnel work  toward developing a master production schedule. Although manufacturing  people will have a major input in determining the schedule and a major  responsibility for making it work, marketing and finance will also have  important inputs and responsibilities. The rationale for having these functional  areas work together is the increase likelihood of developing a plan that works  and with which everyone can live.

Moreover, because each of these functional  areas has been involved in formulating the plan, they will have reasonably  good knowledge of the plan and more reason to work toward achieving it.  In addition to the obvious manufacturing resources needed to support the plan,  financing resources will be needed and must be planned for, both in amount  and timing. Similarly, marketing resources will also be needed in varying  degree throughout the process. In order for the plan to work, all of the  necessary resources must be available as needed. Often, an initial plan must be  revised based on an assessment of the availability of various resources.

Once  these have been decided, the master production schedule can be firmed up.  At this point, material requirement planning comes into play generating  material and schedule requirements. More detailed capacity requirement  planning must be made next to determine whether these more specific  requirements can be met. Again some adjustment in the master production  schedule may be required.  As the schedule unfold, and actual work begins, a variety of reports help  managers to monitor the process and to make any necessary adjustments to  keep operations on track.  In effect, this is a continuing process where the master production schedule is  updated and revised as necessary to achieve corporate goals.

The business plan  that governs the entire process usually undergo changes too although this tend  to be less frequent than the changes made at lower levels (i. e. the master  production schedule).    Finally, it should be noted that most MRP 11 systems have the capability of  performing simulation, enabling managers to answer a variety of "what if”  questions so they can gain a better appreciation of available options and their  consequences. 

4.0 CONCLUSION
 In this note, you have learnt the meaning of MRP and the conditions under  which it is appropriate; its inputs and outputs as well as the nature of MRP  processing; the benefits, requirements and the difficulties encountered with its  use. 

5.0 SUMMARY 
Material requirements planning (MRP) is an information system used to handle  ordering of dependent-demand items (i e, components of assembled products).  The planning process begins with customer orders, which are used along with  any back order to develop a master schedule that indicates the timing and  quantity of finished items. The end items are exploded using the bill of  materials, and material requirements plans are developed that show quantity  and timing for materials, and timing for ordering or producing components.  The main features of MRP are the time-phasing of requirements, calculating  component requirements, and planned-order releases. To be successful, MRP  requires a computer program and accurate master production schedules, bills of  materials, and inventory data. Firms that have not had reasonably accurate  records or schedules have experienced major difficulties in trying to implement  MRP.  MRP 11 is a second-generation approach to planning which incorporates MRP  but adds a broader scope to manufacturing resource planning because it links  business planning, production planning, and the master production schedule. 
.  

0 comments:

Post a Comment

DH